En tiedä miten ajantasaisesti Ukrainan verkko-operaattorin sivut toimivat, mutta ovat ilmeisesti "saarikäytöllä" eli sähköverkko ei ole enää yhteydessä muihin maihin. Verkon toimintaa seuraamalla voi vähän päätellä, onko voimalaitoksiin hyökätty.Tässä myös Ukrainan toiminassa olevista ydinreaktoreista kartta:
![]()
Saa nähdä mitä vaikuttaa maan sähkönsaantiin kun venäläiset "rauhanturvaajat" ottavat ne "turvattavaksi".
EDIT:
On Thursday, February 24, from 7:00 am to 4:20 pm, the level of consumption in the power system decreased from 18.3 GW to 15.8 GW. Currently, the level of consumption begins to increase before the evening peak: as of 17:00 – 16.1 GW. The load of the NPPs is 10.98 GW, TPPs – 3.3 GW, HPPs – 1.39 GW.
Large-scale generation facilities, except Luhanska TPP, are operating in a normal way. Despite the explosion near the power plant and damage to the high-voltage line, currently, there are two power units (№1 and №4) operating at Trypilska TPP with a total load of 203 MW.
13 out of 15 NPP power units are in operation. Only 1 power unit №10 of Luhanska TPP is in emergency repair, due to lack of fuel 2 power units at Trypilska TPP are not operating, as well as one at Kharkiv CHP-5, Kyiv CHP-5, and CHP-6.
Operation of power grids
OHL Trypilska TPP – Novokyivska was damaged. At the same time, Trypilska TPP operates at full capacity (209 MW).
OHL 35 kV Verkhnya Typlovska – Plotyna was disconnected from the distribution network of Luhansk Energy Association LLC at 7 am due to the damage, and OHL 35 kV Raihorodska-Shchastya was disconnected at 8 am.
Dispatch service personnel of DTEK Odesa power grids was evacuated due to explosion.
Dispatch service personnel of Bakhmut regional network service centre of NPC Ukrenergo was evacuated due to hostilities.
RES curtailment
From 8:56 to 13:38 due to the significantly reduced level of consumption in the power system, commands were given to unload RES (via RES curtailment management system) for a total of 897 MW, as well as commands for RES unloading due to operational security reasons. As of 17:00, RES load was 80 MW.
Large-scale generation facilities, except Luhanska TPP, are operating in a normal way. Despite the explosion near the power plant and damage to the high-voltage line, currently, there are two power units (№1 and №4) operating at Trypilska TPP with a total load of 203 MW.
13 out of 15 NPP power units are in operation. Only 1 power unit №10 of Luhanska TPP is in emergency repair, due to lack of fuel 2 power units at Trypilska TPP are not operating, as well as one at Kharkiv CHP-5, Kyiv CHP-5, and CHP-6.
Operation of power grids
OHL Trypilska TPP – Novokyivska was damaged. At the same time, Trypilska TPP operates at full capacity (209 MW).
OHL 35 kV Verkhnya Typlovska – Plotyna was disconnected from the distribution network of Luhansk Energy Association LLC at 7 am due to the damage, and OHL 35 kV Raihorodska-Shchastya was disconnected at 8 am.
Dispatch service personnel of DTEK Odesa power grids was evacuated due to explosion.
Dispatch service personnel of Bakhmut regional network service centre of NPC Ukrenergo was evacuated due to hostilities.
RES curtailment
From 8:56 to 13:38 due to the significantly reduced level of consumption in the power system, commands were given to unload RES (via RES curtailment management system) for a total of 897 MW, as well as commands for RES unloading due to operational security reasons. As of 17:00, RES load was 80 MW.